Following damage inflicted by a crash on Gilberdyke Slipper Bridge near Goole in East Yorkshire, the county council identified significant repairs and improvements to the bridge that would extend its life and prevent similar incidents in future. The bridge carries the B1230 over rail lines, and is vital for local access to the M62 motorway, requiring care to be taken to avoid disruption to either road or rail infrastructure.

Client
East Riding of Yorkshire Council
Duration
4 months
Location
Goole
KEY STATISTICS
4
new crash barriers
2
transport routes remained open
PROJECT SCOPE

Spencer Bridge Engineering were appointed to conduct major maintenance works to the single span steel arch structure as well as the re-development and improvement of all four crash barriers on the approach to the bridge in order to prevent a repeat incident.

The project team planned in significant refurbishment works to the rest of the bridge’s structural elements, including re-painting, concrete repairs, joint repairs and bearing replacements. Spencer Bridge Engineering’s sister group, Spencer Rail Engineering’s, depth of expertise in the rail sector was a significant advantage in the planning of these works, with engineers able to plan around the live track below and avoid causing disruption to its normal operation

Have a bridge project you want to discuss?

We work closely with clients from the earliest stages to develop practical, deliverable engineering solutions for complex bridge structures. By combining early contractor involvement, specialist technical expertise, and real-world delivery experience, we help shape projects that are safer, more efficient, and built for long-term performance. Get in touch to discuss your project and explore how early collaboration can reduce risk, improve constructability, and support successful outcomes.

PROJECT OUTCOME

Spencer Bridge Engineering were able to successfully complete the Slipper Bridge project whilst keeping it open to traffic throughout the project, as well as allowing trains to pass on the line below. Significant structural improvements were delivered, repairing the crash damage and carrying out maintenance work to other elements of the bridge to extend its life and reduce the need for future works to be carried out.

The safety of the bridge, road and rail line were also greatly improved with the addition of the new crash barriers.

Spencer Bridge Engineering’s collaborative approach to planning and delivering this project formed an excellent relationship with the client and led to the award of subsequent projects in the county.  